SOP for the Operation of VORTEX MIXTURE
1.0 PURPOSE
This document details the procedure for the Operation of VORTEX MIXTURE
2.0 SCOPE
This procedure
is to be applied at the time of Operation of VORTEX MIXTURE
3.0 RESPONSIBILITY
Persons
along with their responsibilities are given below:
S. | Designation | Responsibility
|
01 | Analyst | To prepare the |
02 | Section In Charge | To ensure |
03 | Quality Assurance | To ensure |
4.0 PROCEDURE
4.1 OPERATION
4.1.1 Switch on the main power supply.
4.1.2 Put on the closed container on plate.
4.1.3 Switch on instrument switch.
4.1.4 Set the speed (low/ or high) as
required for that time
4.1.5 Switch off the instrument switch
4.1.6 Switch off the main power supply
4.2
CLEANING
4.2.1 Clean the instrument with Clean
Cloth.
4.3 Precaution:
4.3.1 Hold the container at such an angle that
it should not slip from hands of the user & the breakage should be avoided.
4.3.2 Beware of the accidents.
5.0 ABBREVIATION
QC Quality Control
SOP Standard
Operating Procedure
6.0 REFERENCE
6.1 Based on Demonstration given by the
Services Engineer
Recorded The Data on Appendix I format No.
APPENDIX
I
LOG
BOOK FOR VORTEX MIXTURE
Name
of the Instrument : VORTEX MIXTURE
Instrument ID
No. :
Location :
S. No.
| Date | Sample | Test | Report no | Analysed | Checked by | Remarks |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|